Rio Tinto
Institution - official statements with no named speaker · GBR
Track record: No forecast checked yet (71 not due, 107 being checked).
178forecasts & commitments on the record
58%can be checked as stated
37average ambiguity (0-100)
0goalpost moves recorded
0confirmed U-turns
Timeline
came true partly did not not due / being checked / too vague
Calibration score: shown after 10 checked forecasts with a stated likelihood (now 0).
How they speak about the future: based on data 176, stated on authority 2.
Kinds of claim: forecast 153, commitment 13, mixed claim 12. · Download this report card as a picture
In the nine words
πρόγνωσιςInference from evidence164 · 92%χρησμοδοσίαInstitutional delivery13 · 7%μαντείαInspired knowledge1 · 1%
How to read this
Each box is one sentence a public figure or institution said about the future, word for word, with a link to the official text. Can be checked means it names what will happen, by when, and how likely - so it can be compared with official figures later. Too vague to check means it does not. Ambiguity (0-100) is how many different ways the sentence can be read. When the date passes, the forecast is compared with official data and marked came true, partly or did not come true. Labels judge the sentence, never the person. Full guide and glossary.On the record (178)
Our major projects remain on schedule and budget, underwriting our growth profile to 2030.
We remain on track for a $1.8 billion annualised productivity benefit run-rate by the end of 2026.
Iron & Titanium Project: Zulti South Location: Richards Bay, South Africa Ownership: Rio Tinto (74%), Blue Horizon Investments (24%) and Employee Share Participation Trust (ESPS) (2%) Capacity: Extend mine life to 2050 Approval: March 2026 Planned first production: Q4 2028 To note: Construction commenced in H1 2026 and will take 30 months to be completed with initial commercial production expected …
Lithium Project: Rincon expansion Location: Salta province, Argentina Ownership: Rio Tinto (100%) Capacity: 60ktpa (battery grade lithium carbonate) Approval: December 2024 Planned first production: 2028 with three-year ramp-up to full capacity To note: Project consists of the 3ktpa starter plant and 57ktpa expansion program.
This new capacity is expected to be in addition to 30,000 tonnes of new recycling capacity at Arvida, which has been rescheduled to open in H1 2027. $1.5bn • Construction is nearing completion and demobilisation is underway. • Pot commissioning and ramp-up will continue through 2026, with full capacity targeted during 2027.
The project will allow mining to continue into a new area of the orebody between 2026 and 2032. $1.8bn • Stripping will continue through 2027 with sustainable ore production from the second phase of the pushback expected to be reached in H2 2027.
reporting periods beginning on or after from 1 January 2027 and will replace IAS 1 “Presentation
ended 30 June 2026 and likely future developments are given on pages 2 to 24.
•Stripping will continue through 2027 with
Agreement.Construction starts in 2026 with commissioning expected in 2028.
Opportunities to release around $5 billion by the end of 2026 are
we announced we will reduce production by 40% from October 2026 to extend its life until
Chinese economy: industrial production slowed to 4.3% in April and May from 6.1% YoY in Q1, partly reflecting lower oil supply entering the industrial production value chains.
Engineering for the Bécancour facility has been completed and construction is now more than 70% advanced. • Whabouchi and Galaxy mines: we are continuing a strategic business and capital discipline review with our partners in Canada to decide which of the two mines we will develop.
SimFer port commissioning is expected in Q1 2027. • Workforce across all the SimFer scope of mine, rail and port is 19,460 with 76% Guinean participation.
Engineering for the Bécancour facility has been completed and construction is now more than 70% advanced. • Whabouchi and Galaxy mines: we are undertaking a strategic business and capital discipline review with our partners in Canada to decide which of the two mines we will develop.
The mine is expected to have a 40-year5 life and operate in the first quartile of the cost curve. $2.5bn • Starter plant: commissioning completed in 2025, with ramp-up activities continuing to progress toward full capacity by the end of 2026. • Construction of full scale plant continues on schedule across key areas, including earthworks, camp expansion, concrete works, and …
SimFer port commissioning is expected in Q1 2027. • Workforce across all the SimFer scope of mine, rail and port is 20,700 with 77% Guinean participation.
Commissioning of common rail infrastructure completed in Q1 2026, and we expect a 30 month ramp-up to full production rates during H2 2028. • Non-managed infrastructure – our partners confirm that construction is progressing well and is on track. • SimFer mine5 is progressing to plan, with 74% completed – bulk earthworks and permanent process facilities construction continue.
Aluminium Project: Low-carbon AP60 aluminium smelter Location: Quebec, Canada Ownership: Rio Tinto (100%) Capacity: Project will add 96 new AP60 pots, increasing AP60 capacity by 160,000 tonnes of primary aluminium per annum Approval: June 2023 Start date: First hot metal and commissioning achieved in March 2026, smelter fully ramped up by end of 2026.
SimFer port commissioning expected in Q1 2027. • Workforce across all the SimFer scope of mine, rail and port has reached 26,700 with 82% Guinean participation.
Commissioning of the common rail to port infrastructure will be a complex process, and once complete, around the end of Q1 2026, we expect a 30 month ramp-up to full capacity. • Non-managed infrastructure - our partners confirm that construction is progressing well and is on track. • SimFer mine5 is progressing to plan, with 62% completed - bulk earthworks …
Commissioning planned to commence in 2026 ahead of first production in 2028. • Whabouchi and Galaxy mines: we are undertaking a strategic business and capital discipline review with our partners in Canada to decide which of the two mines we will develop.
Aluminium Project: Low-carbon AP60 aluminium smelter Location: Quebec, Canada Ownership: Rio Tinto (100%) Capacity: Project will add 96 new AP60 pots, increasing AP60 capacity by 160,000 tonnes of primary aluminium per annum Approval: June 2023 Planned start date: First hot metal and commissioning is expected by Q1 2026, smelter fully ramped up by end of 2026.
This additional output is excluded from the production tables in this report for 2025; however, we will be including the additional output from 2026 and reporting QAL on a 100% basis.
Vaudreuil returned to normal operations post a planned shutdown in Q3. • At Yarwun, we announced that we will reduce production by 40% from October 2026, to extend the operation’s life until 2035 and allow time to explore further life-extension and modernisation options.
The value of the projected initiatives may not fully deliver the expected benefit, hence a pre-tax impairment charge of $122 million (post-tax $86 million) has been allocated to property, plant and equipment.
These royalty receivables include US$104 million from forecast production beyond 2030.
A further US$500 million will be invested once a decision is made to proceed with the project, towards construction costs, and an additional US$50 million if the joint venture achieves its aim of delivering first lithium by the end of 2030.
Amendments to IFRS 9 Financial Instruments and IFRS 7 Financial Instruments: Disclosures (mandatory in 2026) will help companies better report the financial effects of nature-dependent electricity contracts, which are often structured as power purchase agreements (PPAs).
On 6 March 2025, we announced we will invest $1.8 billion to develop the Brockman Syncline 1 mine project (BS1), extending the life of the Brockman region in the West Pilbara of Western Australia and sustaining production from the company's world class iron ore operations.
•Total project costs have increased by $155m to ~$1.3bn (previously $1.1bn) primarily due to contractor performance challenges, external cost inflation and adjustments in delivery model, and commissioning is now expected by Q1 2026 (previously H1 2026) four months faster.
Project Total capital cost (100% unless otherwise stated) Status/Milestones Lithium Project: Rincon expansion Location: Salta province, Argentina Ownership: Rio Tinto (100%) Capacity: total of 60kt per year (battery grade lithium carbonate) Approval: Dec 2024 Planned first production: 2028 with three-year ramp-up to full capacity To note: Project consists of the 3kt starter plant and 57kt expansion plant.
However, output was reduced at the concentrator due to lower weight yield (vs ore planned) which will be addressed as we make changes to the mine plan over the next few months.
“We will continue to drive progress towards our long-term strategy to deliver profitable growth, attractive shareholder returns and build a stronger, more diversified business.” 1.
We will design, engineer and build a demonstration plant equipped with ten pots operating at 100 kiloamperes (kA), for a total investment of $285 million (Rio Tinto $179 million, Government of Quebec $106 million).
Development of the Oyu Tolgoi underground copper-gold mine in Mongolia (Rio Tinto 66%), which is expected to produce (from the open pit and underground) an average of ~500,000 tonnes⁸ of copper per year from 2028 to 2036. $7.06bn $0.5bn First ore on the conveyor to surface belt was achieved in October 2024, with the conveyor system now able to transport …
The project will allow mining to continue into a new area of the orebody between 2026 and 2032. $1.8bn $0.9bn Approved in December 2019, stripping commenced in 2020 and will continue through 2027.
We also made commitments to projects that are expected to deliver abatement of around 3.6Mt per year in 2030, mostly through renewable electricity and biofuels.
Our operational performance is improving: in 2024, we delivered over 1% production growth and a 3% increase in sales volumes, both on a copper equivalent basis (based on long-term consensus pricing), and by the end of the year we had commenced deployment of SPS at 31 (~80%) of our sites.
Up to 2030, cumulative decarbonisation capital is expected to be at the lower end of our $5 to $6 billion range, subject to Traditional Owner and other stakeholder engagement, regulatory approvals and technology developments, due to the increased role of commercial partnerships.
Once completed, the project will add 96 new AP60 pots, increasing AP60 capacity by 160,000 tonnes of primary aluminium per year by the end of 2026.
Commissioning activities commenced during the quarter and are forecast to be progressively completed through to the second quarter of 2025. • Construction of primary crusher 2 is progressing to plan and remains on track to be completed by the end of 2025.
First production is expected in 2028 with a three-year ramp-up to full capacity.
Our guidance on capital spending on decarbonisation projects to 2030 is maintained at $5 to $6 billion (lower end).
We will now work to finalise definitive agreements in the first half of 2025, along with formalising the broader strategic partnership. • Titanium dioxide slag production of 990 thousand tonnes in 2024 was 11% lower than 2023 due to reduced market demand.
We will continue to develop and operate Winu as managing partner and SMM will pay $195 million upfront, and $204 million in deferred consideration, contingent on milestones and adjustments to be agreed.
The PFS, which is targeting an initial capacity of up to 40 million tonnes per year, subject to relevant approvals, is expected to be completed in 2025.
Development of the Oyu Tolgoi underground copper-gold mine in Mongolia (Rio Tinto 66%), which is expected to produce (from the open pit and underground) an average of ~500,000 tonnes8 of copper per year from 2028 to 2036.
Announced in December 2023, first production at the Simfer mine is expected in 2025, ramping up over 30 months to a 60 million tonne per year capacity (27 million tonnes Rio Tinto share).
Showing the newest 50 - the ledger has all 178.